Construction and Mechanic’s Liens

Construction & Mechanic’s Liens

Two six-month deadlines. Miss either one and the lien is gone.

Missouri’s mechanic’s lien statute is unforgiving on process — and powerful for anyone who follows it.

Schedule a Free Consultation(314) 732-1547

The deadlines that decide these cases ↓

Missouri’s mechanic’s lien law, Chapter 429, RSMo, gives contractors, subcontractors, suppliers and design professionals a security interest in the property they improved. It is a strong remedy and a technical one. Nearly every lien that fails in Missouri fails on a deadline or a notice requirement rather than on whether the work was performed or the money was owed. This page sets out the sequence, the two separate six-month periods, the notices that are conditions precedent, and what an owner can do on the other side.

There are two six-month deadlines, and they are not the same deadline. Under § 429.080, RSMo, the lien statement must be filed with the circuit clerk within six months after the indebtedness accrued. Under § 429.170, an action to enforce the lien must be commenced within six months after filing the lien statement. Filing on time and then failing to sue within six months of the filing extinguishes the lien as surely as never filing at all. Claimants routinely lose on the second deadline because the first one felt like the finish line.

The notices

Two notices that are conditions precedent, not formalities.

Construction work on a Missouri property

The ten-point bold notice. Section 429.012, RSMo requires an original contractor to give the owner a written notice, in ten-point bold type, warning that persons supplying labor or materials may claim a lien if they are not paid. The statute prescribes the substance, and Missouri courts treat compliance as a condition precedent to the original contractor’s lien rights. A contractor who never gave the notice does not have a defective lien; they generally have no lien.

The ten-day subcontractor notice. Under § 429.100, RSMo, every person other than the original contractor must give the owner or the owner’s agent ten days’ notice before filing the lien, stating that the claimant holds a claim, the amount, and from whom it is due. This is how an owner learns that someone down the chain has not been paid — and it is why an owner should never ignore one.

Residential forfeiture. Section 429.016, RSMo addresses residential work and contains a forfeiture provision for noncompliance with its requirements. Residential projects carry their own set of rules that do not apply to commercial work, and the consequences of missing them are severe.

The sequence

From last day on the job to judgment.

1. Notice

The original contractor’s § 429.012 ten-point bold notice must have been given — at the outset of the relationship, not at the end. Everyone else gives the § 429.100 ten-day notice before filing.

2. File the lien statement

Within six months after the indebtedness accrued, file with the clerk of the circuit court of the county where the property lies — § 429.080, RSMo. The statement must include a just and true account of the demand, a correct description of the property, and be verified by affidavit. Overstating the claim is a real risk, not a negotiating posture.

3. Sue within six months of filing

Section 429.170, RSMo requires the enforcement action to be commenced within six months after filing the lien statement. This is the deadline claimants miss.

4. Enforce

The suit resolves the validity and amount of the lien and, if successful, produces a judgment enforceable against the property. Lien claims are frequently joined with breach of contract and quantum meruit counts, because the personal claim survives even where the lien fails on a technicality.

If you are the owner

A lien on your property when you already paid the contractor.

A Missouri home under renovation

This is the situation owners find least fair and it is entirely lawful. A subcontractor or supplier who improved the property and was not paid by the general contractor may lien the property even though the owner paid the general in full. The lien attaches to the improvement, and the owner’s payment upstream does not discharge it.

Prevention is procedural and it works. Require conditional and unconditional lien waivers from the general contractor and from every subcontractor and supplier with each payment. Ask for a list of subcontractors and suppliers at the outset and keep it current. Consider joint checks on large trade payments. Do not make the final payment until the waivers are in hand.

Once a lien is filed, the practical options are to pay and take a release, to negotiate, to bond around the lien so a sale or refinance can proceed, or to litigate the lien’s validity — and validity challenges in Missouri very often turn on the notices and the deadlines rather than on the work. The § 429.012 notice, the § 429.100 notice, the § 429.080 filing date and the § 429.170 suit date are the first four things to check.

A recorded lien clouds title and will stop a sale or a refinance regardless of its merits. If a closing is pending, that timing pressure is itself part of the negotiation. See buying and selling property and property disputes.

Most lien disputes are contract disputes wearing a statute. The lien is security; the underlying claim is for money owed under an agreement. That is why the contract matters so much: a written scope of work, a payment schedule tied to defined milestones, a change order procedure requiring signatures before extra work begins, and a retainage provision resolve most of what later becomes litigation. If you are a contractor whose contracts are a one-page estimate, the lien statute will not rescue what the paperwork gave away. See business law and business litigation.

Meet Derek Haake

Property is where his other three practices meet.

Derek R. Haake, Attorney

Real estate is rarely only real estate. A house is the largest asset in most estates, which is why Derek spent three years as a Vice President and Estate Settlement Officer at Bank of America Private Bank dealing with title, deeds, and property that had to be sold or transferred after a death. It is frequently the largest asset in a divorce, and the thing a business actually operates out of.

He drafts the documents and he litigates them — almost fifteen years of it. Boundary disputes, quiet title actions, contract fights and fiduciary claims are ordinary work here, and so is the deed that prevents one. He holds an MBA alongside his law degree.

What that means practically: a property question gets answered with the estate consequence, the tax consequence and the business consequence in view, rather than as an isolated transaction. See estate planning, business law and family law.

Schedule a Free ConsultationRead Full Bio

Questions

Missouri mechanic’s liens, answered.

How long do I have to file a mechanic’s lien in Missouri?

Six months after the indebtedness accrued, under § 429.080, RSMo. The lien statement is filed with the clerk of the circuit court in the county where the property is located, and it must contain a just and true account of the demand due after all credits, a correct description of the property, and verification by affidavit. When the indebtedness “accrued” is usually tied to the last date of substantial work or delivery of materials on the project — not to the date an invoice went unpaid, and not to warranty or punch-list work performed later to extend the deadline. If your calculation of the accrual date is what stands between you and a lien, get it reviewed rather than assumed.

I filed my lien. Am I done?

No, and this is the single most common way Missouri lien claimants lose. Section 429.170, RSMo requires that an action to enforce the lien be commenced within six months after filing the lien statement. The filing preserves the claim; the suit enforces it. A claimant who files a perfect lien statement on time and then spends eight months negotiating with the owner has an expired lien and nothing but a contract claim. Calendar the enforcement deadline the day you file, and treat settlement discussions as running in parallel with suit preparation rather than in place of it.

Do I have to give notice before filing a lien?

Yes, and which notice depends on who you are. An original contractor — one in direct contract with the owner — must have given the owner the written notice required by § 429.012, RSMo, in ten-point bold type, warning that persons supplying labor or materials may claim a lien. Missouri courts treat that notice as a condition precedent to lien rights, so it has to have been given as part of the contracting process, not manufactured afterward. Everyone else — subcontractors, sub-subcontractors, suppliers — must give the owner or the owner’s agent ten days’ notice before filing, under § 429.100, stating the claim and the amount and from whom it is due.

A subcontractor filed a lien but I already paid my contractor in full. Is that legal?

Unfortunately, yes. Missouri’s lien attaches because the property was improved and the improver was not paid; it does not depend on whether the owner paid someone else. If a general contractor takes the owner’s money and does not pay the plumbing subcontractor, the plumber can still lien the property. That result feels wrong to owners and it is the reason lien waivers exist. The protection is procedural: conditional waivers with each progress payment, unconditional waivers when funds clear, waivers from every tier and not just the general, a current list of subcontractors and suppliers, joint checks on large trade payments, and no final payment until the file is complete. If a lien is already filed, check the notices and the two deadlines first — that is where invalid liens are found.

What is a lien waiver and should I sign one?

A lien waiver is a document in which a contractor, subcontractor or supplier gives up lien rights for work performed or payment received. There are two important distinctions. A conditional waiver takes effect only when the payment actually clears; an unconditional waiver takes effect on signature regardless of whether the cheque is good. And a waiver may be limited to a progress payment through a stated date, or it may be a final waiver covering everything. Contractors should sign conditional waivers for progress payments and reserve unconditional final waivers for funds already received. Owners should collect them at every tier with every payment. Read what you are signing: an unconditional final waiver signed in exchange for a promise is a gift.

Can I still sue if my lien deadline passed?

Usually yes, on the contract. The mechanic’s lien is a security interest in the property; it is not the debt. If the § 429.080 filing deadline or the § 429.170 enforcement deadline has run, the claim against the property is gone but the claim against the party who agreed to pay you generally survives, subject to the ordinary contract limitations period. Breach of contract, quantum meruit and unjust enrichment counts are the usual vehicles. What you lose is the leverage: a lien clouds title and stops a closing, while a contract judgment has to be collected from whatever assets the defendant has. That difference is exactly why the deadlines are worth calendaring. See business litigation.

Does a mechanic’s lien have priority over the construction loan?

This is one of the more technical questions in the area and it is genuinely fact-dependent. Priority disputes between mechanic’s lien claimants and deeds of trust turn on the timing of the commencement of the work relative to recording of the security instrument, on the character of the improvements, and on doctrines Missouri courts have developed around when lien rights relate back. The stakes are large, because in a foreclosure the priority order decides who is paid and who is not. If you are a lender, a title insurer, a claimant, or an owner with a project that has stalled with a construction loan on it, this is not a question to resolve from a general description — the analysis depends on recorded dates and on what was visible on the ground when the deed of trust was recorded.

Are residential projects different?

Yes. Section 429.016, RSMo sets out requirements applicable to residential work and includes a forfeiture provision for failing to meet them — meaning a claimant who does not comply can lose lien rights entirely, not merely face a defect. Residential owners are also the people least likely to know that a subcontractor can lien their home after they have paid the general contractor, which is part of why the statute treats residential work distinctly. Contractors doing residential work in Missouri should have the notice and documentation practice built into their standard process rather than assembled per project; homeowners should insist on waivers even on modest jobs. Getting this reviewed once, at the level of your standard contract and forms, is far cheaper than getting it litigated.

What should the lien statement actually say?

Section 429.080, RSMo requires a just and true account of the demand due after all just credits have been given, a correct description of the property to be charged, and verification by the claimant’s affidavit. Each of those is a place liens fail. “Just and true” means the amount has to be right — a lien inflated to create negotiating room can be attacked as not being a just and true account, which risks the entire lien rather than just the excess. The property description must be legally correct; a street address is generally not a description of the property. And the affidavit must be properly made. Have the statement prepared or reviewed by someone who does this work; the filing fee is small and the cost of a defective statement is the whole claim.

Can a design professional or an equipment supplier file a lien?

Chapter 429 extends lien rights beyond the trades who swing hammers, and Missouri law addresses claims by those who furnish materials, machinery and certain professional services in connection with an improvement. Whether a particular claimant qualifies, and what notices apply to them, depends on their relationship to the owner and to the improvement — the original contractor / non-original contractor distinction in § 429.012 and § 429.100 drives which notice you owe. Rental equipment, off-site fabrication, and design work performed before construction begins each raise their own questions. If you are in one of those categories, confirm your rights and your notice obligations at the start of the project, not when payment stops.

Can I bond around a lien so my closing can go forward?

Generally yes, and it is often the practical answer when a lien is blocking a sale or a refinance. Bonding around substitutes a surety bond for the property as the security for the claim: the lien is released of record, the closing proceeds, and the dispute continues against the bond rather than against the real estate. That separates the merits of the payment dispute from the transaction deadline, which is usually where the pressure is coming from. The mechanics, the amount required, and the title insurer’s willingness to insure over the released lien all need to be coordinated before the closing date, so raise it early. The alternative — paying the claim under protest to clear title — also works but generally costs more and forfeits leverage.

My contractor abandoned the job. What are my options?

Three tracks, and they run at once. First, secure the site and document everything: photographs of the current state, the contract and every change order, all payments made, and a written record of the abandonment and of your attempts to get the contractor back. Second, deal with the money — a contractor who has been paid ahead of the work owes the difference, and a breach of contract claim measures your damages by what it costs to complete the work properly, so get real completion bids rather than estimates. Third, protect the property from liens: subcontractors and suppliers who were not paid by the departed general can still lien your home, so find out who they are, ask for the § 429.100 notices, and get waivers from anyone you pay directly. If the contractor was licensed or bonded, there may be additional remedies. See general litigation.

Contractors and owners

The lien statute rewards the party who kept the paperwork.

Whether you are trying to get paid or trying to clear a lien from your title, the answer usually turns on notices and dates. Bring the file and we will tell you where you stand.

Schedule a Free Consultation(314) 732-1547

Email derek@haakelawgroup.com · Offices in Wildwood, MO & St. Louis, MO (by appointment)

This page is general information about Missouri law, not legal advice, and does not create an attorney-client relationship. Property rights depend on the specific instruments, the legal description, and the facts of each parcel. Consult a licensed attorney about your situation.

Scroll to Top